Skip to content
Anzma modulePart of Purchases

Procurement cycle software and system: requests, RFQs, quote comparison and approval

From a department’s need to the purchase order: an approved request, an RFQ sent to several suppliers, a side-by-side comparison and an award that creates the orders.

Last updated: 9 min readBe the first to rate this page
Procurement cycle software and system: requests, RFQs, quote comparison and approval

In short

Anzma’s procurement cycle starts with a purchase request from a department, then an RFQ to suppliers, a comparison of their quotes and approval of the best, before it becomes a purchase order. Each supplier enters price and lead time on a private link, or the buyer keys them in, and a matrix highlights the cheapest per line. On award, purchase orders are created at the agreed prices, and a cycle-time report measures request to order to bill.

Who is it for?

  • Contractors
  • Factories
  • Supply companies
  • Pharma companies
  • Purchasing departments
  • Department heads
Steps
Request, approval, RFQ, comparison, award, purchase order
Request approval
By permission, with optional auto-approval up to an amount
Supplier quotes
Via a private link per supplier, or entered by the buyer
Default deadline
7 days to quote, adjustable
Award
To one supplier or line by line
Reports
Request status, quote comparison and cycle time

What you get, at a glance

  • Department purchase requests

    A department records its need with items or free-text lines, quantities, estimated price, suggested supplier and needed-by date, on a branch and cost center.

  • Approval before buying

    A request is submitted, then approved or rejected with a reason by someone holding the permission, with optional auto-approval for small ones.

  • RFQ to several suppliers

    Pick suppliers and email each an RFQ with a private link where they enter price and lead time before the deadline.

  • Side-by-side comparison

    A matrix of suppliers and lines highlights the cheapest price per line and shows each supplier’s total with tax and lead time.

  • Award creates the POs

    Award the whole RFQ to one supplier or split lines across several, and purchase orders are created at the quoted prices.

  • Cycle time measured

    A report averages the days from request to purchase order and from order to bill, so you see where purchasing slows down.

Inside the product

Quote comparisonSupplier prices per line with the cheapest highlighted (illustrative view).
On this page
Section 01

What is the procurement cycle?

The procurement cycle is the chain of steps a purchase passes through, from the moment a need appears until the supplier is paid: a department request, approval, quotes, choosing a supplier, a purchase order, receipt and bill, then payment. Its aim is that what is bought is really needed, at the best price, with approval from the right person and a clear financial effect.

It goes by several names: purchase-to-pay, the requisition-to-PO process, the document flow of purchasing. It is not a single law but an internal policy each company sets, and its strictness varies from a small shop buying on a verbal request to a contractor that demands several quotes and written approval.

In Anzma this is the procurement cycle module (key purchase_cycle), part of the purchasing software line. It covers the first steps: the purchase request, the RFQ and the award. It then hands purchase orders to purchase orders and bills, which carries on with receipt, bill and payment, and the result appears in the supplier statement.

The practical benefit is that every purchase order can be traced backwards: who requested it, who approved it, which quotes were compared before it and why this supplier won. That written trail is what an internal auditor or an owner needs when asking why you bought from this supplier at this price.

Section 02

What are the steps of the procurement cycle, in order?

Six consecutive steps, four in the cycle module and two in purchases. Not every purchase must pass all of them: a small routine purchase may start straight from a purchase order, while a large one goes through everything.

  1. 1

    Purchase request

    The requesting department records items, quantities, needed-by date, estimated price and suggested supplier on its branch and cost center, then submits.

  2. 2

    Request approval

    Someone with the permission approves or rejects with a reason. With auto-approval set up to an amount, smaller requests are approved on submit.

  3. 3

    RFQ

    From an approved request or standalone, choose suppliers and a deadline; each supplier receives a private link to enter price and lead time.

  4. 4

    Compare and award

    Compare quotes in one matrix, then award the RFQ to one supplier or line by line, and purchase orders are created.

  5. 5

    Purchase order and receipt

    The order is approved and sent; when goods arrive it is converted to a bill that brings stock in and posts its entry.

  6. 6

    Payment

    Record the supplier payment from cash or bank and allocate it to bills.

Section 03

Who is responsible for each step?

Anzma assigns responsibility by permission rather than by title, so you distribute roles as you like. The table is a typical split many companies follow, a suggestion rather than a constraint: in small firms one person may hold two roles, but it is safest that nobody requests, approves and pays alone.

A typical split of roles in the procurement cycle
StepRequesterPurchasingManagerFinanceWarehouse
Purchase requestCreatesReviewsApproves--
RFQ-Creates and sends---
Compare and award-AwardsAgrees if needed--
Purchase order-CreatesApproves above limit--
Receipt and bill-Converts-Reviews and issuesConfirms arrival
Payment---Pays-
Section 04

What is the difference between a purchase request, an RFQ and a purchase order?

A purchase request is internal: a department tells the company “we need this”. An RFQ is external: purchasing asks suppliers “what do you charge for this, and in how many days?”. A purchase order is a commitment: the company tells one supplier “we buy this from you at this price”. Each document answers a different question, and their sequence makes a purchase justified and accountable.

In Anzma a purchase request carries the requester, branch, department, cost center and needed-by date. Its lines are catalogue items or free-text descriptions for things with no item, each with quantity, estimated price and a suggested supplier. Statuses are draft, submitted, approved or rejected, then partially ordered or ordered, or cancelled. A rejected request can be reopened for editing, and its status updates itself as purchase orders are raised against it.

The three documents, who issues them and who receives them
DocumentIssued byTo whomWhat it commits
Purchase requestRequesting departmentManagement and purchasingCommits no supplier
RFQPurchasingSeveral suppliersDoes not commit you to buy
Purchase orderPurchasingThe chosen supplierCommits both parties
Section 05

Who approves purchases before spending?

A purchase request is approved by someone holding the permission to approve purchase requests; if a person with that permission submits it, it is approved at once. You can set an amount for automatic approval, so a request whose estimate does not exceed it is approved without waiting. Anything above waits for the approver, who approves or rejects with a reason the requester can read.

A second approval comes at the purchase order itself in purchases: you can require approval above an amount you set, and likewise for bills and returns. Companies needing a multi-level approval path can link order and bill approval to rules from the workflows module.

Approval here is a single step per request, by permission. In the current version no dashboard widget lists requests waiting for approval, so approvers follow them from the request list, filtered by status.

  • Request approval is a separate permission from creating one
  • Optional auto-approval for requests up to an amount you set
  • Rejection with a written reason, and reopening to edit
  • An optional second approval on the order above a threshold
Section 06

How do you request quotes from suppliers?

An RFQ is created from an approved request, which copies its lines, or standalone. You choose the suppliers from contacts and set a deadline (7 days by default, changeable in settings), then send it. Each supplier gets an email with a PDF and a link that is theirs alone, opening a form where they enter the price of each line, lead time, quote validity and notes.

The buyer can key in prices when quotes arrive by phone, WhatsApp or on paper, using the same form under the supplier’s name. A supplier’s link can be revoked and replaced, and the RFQ can be closed early. The link closes automatically after the deadline so no late prices come in.

  • From an approved request or standalone
  • A private link per supplier to enter price and lead time, no account needed
  • Manual entry by the buyer for quotes received by phone or paper
  • Revoke or renew a link, and close the RFQ before its deadline
Section 07

How do you compare supplier quotes and pick the best?

The comparison screen is a matrix: lines in rows, suppliers in columns, each cell showing price and lead time. Anzma highlights the cheapest price per line, computes each supplier’s total with tax, and points to the cheapest supplier who quoted every line. That matters, because a supplier cheaper on one line who left the rest unpriced is not the cheapest for the request.

Price alone does not settle the choice. Consider lead time, quote terms, the supplier’s record in supplier evaluation and their on-time rate. Anzma does not compute a composite score automatically, so the decision stays yours and is documented by the matrix.

Illustrative quote comparison (approximate figures)
LineSupplier ASupplier BSupplier C
Copper cable 100 m4,2004,0504,300
Distribution board9,80010,4009,600
Circuit breakers (10)2,5002,300Not quoted
Quote total16,50016,750Incomplete
Lead time7 days14 days5 days
Section 08

How are quotes awarded and turned into purchase orders?

An award is either to one supplier for all lines, or line by line across several suppliers. On confirming, a purchase order is created for each supplier that won lines, at their quoted prices, with an expected delivery date worked out from the lead time they gave. The order carries the RFQ reference and links to the original request lines, so their ordered quantity updates.

If only some lines are awarded the RFQ is partly closed; if all are awarded it becomes awarded. Orders then follow their usual path in purchases. The winning supplier need not have quoted every line; having a price for the line you award is enough.

Example: you award the cable and breaker lines to supplier B because it is cheapest on both, and the distribution board to supplier C because it is cheapest and fastest. Two orders result: one to B for two lines and one to C for one. Each is approved, sent and billed independently, so neither waits on the other. That flexibility is why line-by-line award beats whole-RFQ award when prices vary.

Section 09

What is the accounting cycle of purchases, and when does the entry start?

The accounting cycle of purchases is the set of entries arising along the document cycle. The rule is that the preliminary steps, from request to purchase order, carry no entry because they create no confirmed financial obligation, and that entries start with the purchase bill and then the payment.

Effect of each step of the cycle on stock and accounts
StepStockJournal entryNote
Purchase requestNo effectNoneAn internal approval document
RFQ and awardNo effectNoneProduces purchase orders only
Purchase orderNo effectNoneA contractual commitment, not posted
Purchase billItems increaseInventory and tax / suppliersThe financial effect starts here
Supplier paymentNo effectSuppliers / cash or bankReduces what is owed
Section 10

What does a good request for quotation contain?

Many people search for a request for quotation template to prepare in a file. Anzma holds the same idea in structured fields, so there are fewer mistakes and comparison is easier later. A clear request needs only a few details, and they must be identical for every supplier so the prices are comparable.

The system prints the RFQ as a PDF with your company header and details, shows the same lines to the supplier on the private link page, and collects replies in the same table. You do not retype figures that reached you in different messages.

  • Items or descriptions with quantities and units identical for all suppliers
  • The quote deadline and the currency requested
  • Notes for the supplier on specifications, supply and delivery terms
  • Unit price and lead time per line and the quote validity from the supplier
  • A private link per supplier instead of one file passed around
Section 11

How do you measure procurement efficiency?

Three ready, exportable reports. The request status report shows what is still draft, submitted, approved or ordered. The quote comparison report shows supplier prices for each RFQ. The cycle-time report works out, per request, the days to the first purchase order, from there to the first bill, and the total, with averages.

If the average from request to order is 12 days and the bill follows twenty days later, you learn the problem is in negotiation or supplier delay, not approval. These numbers only illustrate how to read it; your results come from your data. On that basis a slow department is judged on evidence, not impression.

Section 12

What are common procurement cycle mistakes?

The first is buying before approval, where the order reaches the supplier before the manager agrees, so approval becomes a formality. The second is comparing unequal quotes: a supplier priced better specs, left out tax or delivers to their own site, and looks cheaper when it is not. The third is ignoring lead time, awarding to the cheapest and then a project stalls for two weeks waiting.

The fourth is leaving approved requests hanging with no purchase order, so a department thinks its need has been met. Request statuses solve this: you can see approved requests not yet ordered and partly ordered ones with something left. The fifth is no measurement, so nobody knows how long buying really takes until someone complains. The cycle-time report supplies the number from your own data.

Section 13

How does the cycle work for contractors and factories?

A contractor buys materials for each project in large quantities at changing prices and needs to show that the price paid was the best. The project manager links the purchase request to the project’s cost center, purchasing asks three or more suppliers for quotes, and the award is documented, so the project carries cost at the right price and can be reviewed later.

In a factory the request records the raw materials production needs, and quotes are compared on price and on the lead time that drives the production schedule. How many quotes you need is your company policy; the system sets no minimum. Two or three quotes on large purchases is common, and you follow your internal rules and any government clients’ regulations that apply.

Section 15

Who is procurement cycle software for?

Companies where several people request purchases, the buyer spends company money, and the owner wants assurance that buying is justified, approved and compared. It is enabled in templates such as contracting management software, factory management software, tender and supply management software, pharma company management software, car showroom management software and real estate development software.

A small shop that buys for itself needs only the purchases module. It runs in the browser; there is no native mobile app today. Book an online meeting and we will show the cycle step by step on your business.

Frequently asked questions

What is the procurement cycle?

The steps a purchase passes through from need to supplier payment: purchase request, approval, quotes, choosing a supplier, purchase order, receipt and bill, then payment. It ensures that what is bought is needed, at the best price, with approval from the right person.

What are the steps of the procurement cycle?

A department’s purchase request, its approval, then an RFQ with quotes compared and awarded, then the purchase order, receipt of goods by a bill that brings stock in and posts its entry, and finally paying the supplier. In Anzma receiving happens by issuing the bill with receive stock.

What is the difference between a purchase request, an RFQ and a purchase order?

A request is internal, made by a department to its management. An RFQ is external, asking suppliers for price and lead time without committing you to buy. A purchase order is a commitment addressed to one supplier at an agreed price. Their sequence makes each purchase justified and approved.

How do I compare supplier quotes?

Open the comparison screen to see lines in rows and suppliers in columns, each with price and lead time. Anzma highlights the cheapest price per line and computes each supplier’s total with tax, then you award the whole RFQ or line by line to whoever you choose.

Who approves purchases?

A purchase request is approved by someone holding the permission to approve requests, with optional auto-approval up to an amount you set. A second approval can be required on the order, bill or return above a threshold, or linked to multi-step rules from the workflows module.

How many quotes should I request?

That is your company’s policy, not a limit set by the system. Two or three quotes on large purchases is common, and rules for government clients may demand more. Anzma sends the RFQ to as many suppliers as you choose and compares what comes back.

Does the supplier enter their own price?

Yes. Each supplier receives a private link by email and opens a form to enter price, lead time and quote validity without an account. The link ends at the deadline or when revoked, and the buyer can enter prices themselves if quotes arrive by phone.

How does the cycle work for contractors?

The project manager links the purchase request to the project cost center, purchasing requests quotes from several suppliers, and the award is documented in the matrix. Purchase orders are then created at the approved prices and charged to the project, and the cycle-time report measures how fast it runs.

Is there free procurement cycle software?

We do not offer a free program. Anzma is a subscription service with plans, and you can book a free online intro meeting where we show the cycle from purchase request to award on your own business data. Plans differ in users and branches and are on the pricing page.

Part of the product line

purchasing software

A purchase request, then quotes, a purchase order, receipt, bill and payment, then a statement for every supplier, in one system that updates stock and accounts at each step.

All Purchases modules

Rate this page

Did you find this useful? Your rating helps others.

No ratings yet.

Share this pageWhatsAppXLinkedInFacebook
Pricing

Clear plans that grow with you

Nearly every module in every plan; plans differ by limits.

Basic

For small businesses getting started

450EGP / mo

Billed 5,400 EGP yearly

Save 24%

Includes:

  • 3 users and one branch
  • 150 invoices per month
  • Every module your activity needs
  • 5GB storage
Book a meeting
Most popular

Advanced

For growing businesses with several branches and warehouses

790EGP / mo

Billed 9,480 EGP yearly

Save 20%

Everything in Basic, plus:

  • 7 users, 2 branches and 3 warehouses
  • 750 invoices per month
  • 2 POS devices
  • 15GB storage
Book a meeting

Comprehensive

Everything: unlimited invoices, manufacturing, custom domain and API

1,590EGP / mo

Billed 19,080 EGP yearly

Save 20%

Everything in Advanced, plus:

  • 15 users, 3 branches and 5 warehouses
  • Unlimited invoices
  • Manufacturing, custom domain and API
  • 30GB storage
Book a meeting

Enterprise

For enterprises: open limits, dedicated server and SLA

Custom

Everything in Comprehensive, plus:

  • Unlimited users, branches and warehouses
  • Dedicated server and SLA
  • Storage on demand
  • Account manager and tailored onboarding
Contact us